OnePlan Portfolio Modeler: A Setup Guide for Former Project Online Teams

Writer: Gaurav Wason
Gaurav Wason
Nov 5
5 min read
OnePlan Portfolio Modeler setup guide for teams moving from Project Online

What Are OnePlan Insights?


The OnePlan Portfolio Modeler does the job that Project Online’s Portfolio Analysis used to do. You group candidate projects into a model, set budget and hour limits, and save different mixes as scenarios. Leaders compare them and approve one. Nothing you do in the Modeler changes your live projects.

How does the Modeler compare to Project Online Portfolio Analysis?

Microsoft Project Online retired on September 30, 2026. If your team used its Portfolio Analysis, the OnePlan Modeler does the same job with a simpler setup. Here is how the ideas carry over.

In Project Online

In the OnePlan Portfolio Modeler

Business drivers and driver prioritization

Priority score on each plan

Cost and resource constraint analysis

Targets for budget and hours

Saved portfolio analyses

Scenarios inside a model

Committing selected projects

Save & Commit Scenario


Still sorting out your old Project Online data? Start with our guide to life after Project Online retirement.


What does the OnePlan Portfolio Modeler do?


Most organizations have more project ideas than money or people. The Modeler helps you choose between them.


You gather your candidate projects and set your limits, such as $4 million and 25,000 hours. Then you try different mixes to see which one delivers the most value.


Nothing you do in the Modeler changes your real projects. It’s a safe place to test ideas.

  • Project offices (PMOs) and portfolio managers use it to pick projects.

  • Finance teams use it to see what a budget cut would remove.

  • Executives use it to compare options side by side.


Four terms to know


  • Plan: OnePlan’s word for a project.

  • Model: a saved group of the plans you’re deciding about.

  • Scenario: one set of choices inside a model, such as “$4M budget.” A model can hold several.

  • Target: a limit or goal, such as “stay under $4 million.”

The OnePlan Portfolio Modeler journey: six steps and who owns each

What do you need before you start?


Most first-time problems come from something on this list being missing.

  • Licenses and apps: an Enterprise license for the people who build models [verify]. You also need the Modeler, Financial Plan (for costs) and Resource Plan (for staffing) apps.

  • People: an administrator, one or two planners, and decision makers who can approve (commit) the final scenario.

  • Data for every project: a budget, an expected benefit, a priority score, start and end dates, a financial plan and a resource plan.

  • Agreed targets: your total budget, available team hours and benefit goal.

Tip: Fill in missing data before you build anything. A project with no budget looks free in the Modeler. Keep each model to one decision, such as “next year’s IT projects.”

How do administrators set up the Modeler?


  1. Install the apps. Go to Admin → Apps → [+] Add App [verify]. Install Modeler, Financial Plan and Resource Plan. If Modeler isn’t listed, contact your OnePlan representative.

  2. Give people access. In Resource Center → Configure → Enterprise Security Groups, add planners and decision makers to the right groups.

  3. Add project fields. In Setup → Area Editor → Plan Types, make sure each project type has Budget, Benefits and Priority Score fields on its form.

  4. Fill in the data. Check that cost types such as Budget and Committed Hours exist. Then ask project owners to complete the data listed above.

  5. Create a shared folder. In the Modeler, select New Item → Add Folder. Open the folder’s menu (☰) → Security and add your planners.

Note: Sharing a folder shares every model in it. To share one model, use that model’s own Security option.

How do you build your first scenario in the OnePlan Modeler?


Step 1: Create a model

Select New Item → Add Model and fill in the four tabs.

Tab

What to enter

General

Name, description and folder

Plans

Which projects to include (e.g. project type = IT Project)

Fields

Limits (Budget, Effort), benefits, and sort order (Priority Score)

Resources/Costs

Cost types to load (Budget, Committed Hours)

Don’t skip Resources/Costs. Without it, the Financials and Resources panels won’t appear.
Creating a new model in the OnePlan Portfolio Modeler with the four setup tabs

Step 2: Set targets


Click Targets, enter your limits, and click Apply Targets. Projects that push you over a limit turn red. Projects that help you reach your benefit goal turn green.


OnePlan Portfolio Modeler Targets panel with budget and hours limits

Plans in a OnePlan model shown red or green against targets

Step 3: Adjust and check


  • Drag projects into priority order. Untick any you want to leave out. They drop out of the totals.

  • Click Financials and look for any quarter that goes over budget.

  • Click Resources. Set Data Selection to All Resources and All Plans. Then open Charts → Capacity vs Demand. Bars above the line mean a team is overbooked.

  • Open the Gantt timeline and drag projects to later dates to fix problems. Everything updates instantly.


OnePlan Modeler plan list and Gantt timeline for checking budget and capacity

Step 4: Save


Click Save and name the scenario. Changes you don’t save are lost.


Step 5: Compare scenarios


Make more changes and choose Save → Save Scenario As. Then click Analyze to see your scenarios’ costs, benefits and shared projects side by side.

Analyze view comparing two OnePlan scenarios side by side


Analyze view comparing two OnePlan scenarios side by side

Step 6: Record the decision


When leaders choose a scenario, an approver selects Save → Save & Commit Scenario and clicks Commit. This saves the choices in separate “committed” fields. It doesn’t change live project dates. Project managers update those afterwards.

Save and Commit Scenario menu in the OnePlan Modeler


Save and Commit Scenario menu in the OnePlan Modeler

Commit confirmation for an approved scenario

For OnePlan’s own step-by-step reference, see Build Scenarios for Your Portfolio Models.


What goes wrong most in Modeler setups?


These are the issues we see most when teams start using the Modeler. Most trace back to missing data or a skipped setting.

Problem

Fix

The Financials or Resources panel is missing

Create the model again with cost types selected

Totals look too low

Fill in missing budgets and benefits

Teams look free when they’re busy elsewhere

Choose All Plans in Data Selection

Targets or changes disappeared

Save before leaving the model

Live dates didn’t change after committing

This is expected. Project managers update them.

Frequently asked questions 


Will the Modeler pick projects for me?

No. It shows the effect of each choice, and people decide.

Where does the priority score come from?

In OnePlan’s standard template, it combines four equally weighted ratings on each project. Your organization may have changed this, so check with your project office.


Can I report on scenarios in Power BI?

Yes, through OnePlan’s OData feed in the Integrations app [verify]. The Modeler also has built-in dashboards. If you need custom reports, our Power BI team can build them.


Does committing a scenario change live projects?

No. Committing saves the decision in separate fields. Project managers then update their own plans.


Is the Modeler a good fit after Project Online?

For teams that used Project Online’s Portfolio Analysis, yes. It covers the same decisions: what fits the budget, what fits team capacity, and what to cut. Compare it with other options in our Planner vs FluidPPM vs OnePlan guide.


Get your Modeler set up right the first time

Project Made Easy is a OnePlan Premier Partner with 19+ years in project portfolio management. We set up the Modeler, clean your project data, and train your planners so your first scenario is one leaders can trust. Learn more about our OnePlan consulting and implementation services.



 
 
 